Project Duration

18mths

Project Value

£1.1M

Completion Date

August 2008

In the event of a third dry winter the river abstraction resource at Marham WTWs is vulnerable. Failure of this resource could result in a 13Ml/d demand shortfall.

The objective of this work is to provide an alternative additional resource of 13Ml/d to feed the Marham Supply zone (mostly Wisbech). The result will be the provision of an additional 13Ml/d at Bexwell reservoir.

Anglian Region
This scheme forms part of the Anglian Water AMP4 supply and demand strategy.

Anglian Region
Ensuring additional water resources for the Isleham supply zones

Anglian Region
Provision of a two-vessel solution each rated for 65MLD.

Southern Region
This was a £3M project to provide a new water treatment plant to replace the existing iron removal plant at Goudhurst.